The Maldives Transport and Contracting Company Plc (MTCC) has been contracted to
construct Phase two of V. Keyodhoo harbour on April 10th, 2019. Permanent Secretary at the
Ministry of Planning and Infrastructure, Zeeniya Ahmed Hameed signed on behalf of the
government and the CEO of MTCC Hassan Shah, signed on behalf of the company.
Under this agreement, work carried out will consist of 6300cbm of dredging and excavation
along with construction of a 102M breakwater, 97M of revetment, a 212m quay wall, a ramp,
a concrete bridge, harbor drainage and interlocking pavements.
The project is estimated to cost MVR 29,723,199.91. It is estimated to be completed within 280 days.